Below is a list of proposed or announced projects including ones listed in the AESO queue. A project’s presence on this list only confirms that the project has been publicly announced or listed on the queue. For further info, please connect with the WCDCA for an introduction. Note: locations are not exact - they are approximations mostly to reflect the location’s region.

Please note that this list is for cloud, AI, colo, or crypto projects expected to scale beyond 50MW. Work in progress - WCDCA is not responsible for the accuracy of the information on this page as it may change. Have or know of a project that should be on here but isn’t? Let us know using the contact page on our home page or via our LinkedIn page.

Click on the map icon to see more details about the project on the map. Want to see existing colocation capacity in Alberta instead? Check out Data Center Map.

Western Canada Hyperscale Project Tracker

Proposed Data Centre Locations Map

Proposed Gas Generation (not confirmed for data centre load)

Estimated Total Capex Tracker

Breakdown of Announced Projects by Size

Total Proposed MW (Announced):

Total Proposed New MW Breakdown

By In-Service Date

By Operator (Top 8 Projects by Size)

By Region

Announced Projects

Wonder Valley AI Data Centre Industrial Park

Announced

Location: Greenview, AB, Canada

Size: 7,000 MW

Operator: O'Leary Ventures

End User: Undisclosed (AI-focused)

Details: Announced on December 9, 2024, a $70 billion project to build a 10,000-acre AI data center park. Timeline not specified.

Estimated In-Service Date: Unknown

Type: AI

Power Details: Onsite Gas Gen

Source: Wonder Valley Website

Beacon Langdon Artificial Intelligence Hub

Announced

Location: Rocky View County, AB, Canada

Size: 400 MW

Operator: Beacon Data Centres

End User: Hyperscalers (AI-focused)

Details: Announced in 2025, a 946-acre data center campus near Indus, east of Calgary, with a $4 billion investment alongside a solar farm. Targeting December 2026 energization.

Estimated In-Service Date: December 2026

Type: AI

Power Details: Grid and Onsite Gas Gen (TBD)

Source: AESO Queue and Beacon AI Centers

Beacon Foothills Artificial Intelligence Hub

Announced

Location: High River, AB, Canada

Size: 400 MW

Operator: Beacon Data Centres

End User: Hyperscalers (AI-focused)

Details: Announced in 2025, a $4 billion data center east of High River in Foothills County. Applied on April 8, 2024, with an expected energization date of January 15, 2027.

Estimated In-Service Date: January 15, 2027

Type: AI

Power Details: Grid and Onsite Gas Gen (TBD)

Source: AESO Queue and Beacon AI Centers

Beacon Harry Smith Artificial Intelligence Hub

Announced

Location: Parkland County, AB, Canada

Size: 400 MW

Operator: Beacon Data Centres

End User: Hyperscalers (AI-focused)

Details: Announced in 2025, a 400 MW data center between Keephills and Duffield, west of Edmonton. Applied on April 8, 2024, with an expected energization date of January 15, 2027.

Estimated In-Service Date: January 15, 2027

Type: AI

Power Details: Grid and Onsite Gas Gen (TBD)

Source: AESO Queue and Beacon AI Centers

Beacon Heartland A.I. Hub Load

Announced

Location: Fort Saskatchewan, AB, Canada

Size: 400 MW

Operator: Beacon Data Centres

End User: Hyperscalers (AI-focused)

Details: Announced in 2025, a 400 MW data center east of Edmonton. Applied on May 10, 2024, with an expected energization date of January 15, 2027.

Estimated In-Service Date: January 15, 2027

Type: AI

Power Details: Grid and Onsite Gas Gen (TBD)

Source: AESO Queue and Beacon AI Centers

Beacon Saunders Lake A.I. Hub Load

Announced

Location: Leduc County, AB, Canada

Size: 400 MW

Operator: Beacon Data Centres

End User: Hyperscalers (AI-focused)

Details: Announced in 2025, a 400 MW data center near Edmonton Airport. Applied on May 10, 2024, with an expected energization date of January 15, 2027.

Estimated In-Service Date: January 15, 2027

Type: AI

Power Details: Grid and Onsite Gas Gen (TBD)

Source: AESO Queue and Beacon AI Centers

Beacon Chestermere Data Centre

Announced

Location: Chestermere, AB, Canada

Size: 400 MW

Operator: Beacon Data Centres

End User: Hyperscalers (AI-focused)

Details: Announced in 2025, a $4 billion data center in southern Chestermere, 22 km east of Calgary.

Estimated In-Service Date: Unknown

Type: AI

Power Details: Grid and Onsite Gas Gen (TBD)

Source: AESO Queue and Beacon AI Centers

Beacon Langdon A.I. Hub 2 Load

Announced

Location: Calgary, AB, Canada

Size: 1,400 MW

Operator: Beacon Data Centres

End User: Hyperscalers (AI-focused)

Details: Queued on October 4, 2024, in the AESO interconnection queue. Expected energization date of January 15, 2037.

Estimated In-Service Date: January 15, 2037

Type: AI

Power Details: Grid and Onsite Gas Gen (TBD)

Source: AESO Queue and Beacon AI Centers

eStruxture CAL-3

Announced

Location: Balzac/Rocky View, AB, Canada

Size: 90 MW

Operator: eStruxture Data Centers

End User: Various enterprises

Details: Announced in 2024, a $750 million hyperscale AI data center. Expected to be operational by 2026.

Estimated In-Service Date: End of 2026

Type: Colo

Power Details: Grid

Source: eStruxture Announcement

Bitdeer Fox Creek Crypto Mining Facility

Announced

Location: Fox Creek, AB, Canada

Size: 99 MW

Operator: Bitdeer Technologies Group

End User: Bitcoin mining (Crypto-focused)

Details: Acquired in February 2025 for $21.7 million, a 99 MW data center for crypto mining with a gas-fired power plant, expected to be operational by Q4 2026.

Estimated In-Service Date: Q4 2026

Type: Crypto Mining

Power Details: Onsite Gas Gen

Source: Bitdeer Announcement

Captus Generation Data Centre Site

Announced

Location: Glenwood, AB, Canada

Size: 100 MW

Operator: Captus Generation Ltd.

End User: Various

Details: Captus Generation Ltd 100MW data facility powered by grid and natural gas fired generation. Queued on January 17, 2025, in the AESO interconnection queue. Expected energization date of June 1, 2027.

Estimated In-Service Date: July 1, 2027

Type: Various

Power Details: Grid and Onsite Gas Gen

Source: Captus Website and AESO Dashboard

Calgary A.I. Centre Load

Announced

Location: Calgary, AB, Canada

Size: 50 MW

Operator: Undisclosed

End User: Unknown

Details: Queued on December 19, 2024, in the AESO interconnection queue. Expected energization date of January 15, 2027.

Estimated In-Service Date: January 15, 2027

Type: AI

Power Details: Grid

Source: AESO Queue

Calgary Enterprise A.I. Load

Announced

Location: Calgary, AB, Canada

Size: 100 MW

Operator: Undisclosed

End User: Unknown

Details: Queued on December 19, 2024, in the AESO interconnection queue. Expected energization date of January 15, 2027.

Estimated In-Service Date: January 15, 2027

Type: AI

Power Details: Grid

Source: AESO Queue

Crusoe/Kalina Power AI Data Centers (Myers, Alsike, Crossfield)

Announced

Location: Various (Myers Energy Park, Alsike Energy Park, Crossfield Energy Park), AB, Canada

Size: 420 MW (140 MW per site)

Operator: Crusoe Energy Systems / Kalina Power (KDP)

End User: Hyperscalers (AI-focused)

Details: Signed a framework agreement in March 2025 to develop AI data centers at three sites in Alberta (Myers Energy Park, Alsike Energy Park, Crossfield Energy Park) with natural gas power plants and carbon capture technology. Capacity can go up to 340 MW per site.

Estimated In-Service Date: July 1, 2027

Type: AI

Power Details: Grid and Onsite Gas Gen

Source: Data Center Dynamics Announcement

Genesee Data Centre (1,000 MW)

Announced

Location: Genesee, AB, Canada

Size: 1,000 MW

Operator: Capital Power

End User: Hyperscalers (AI-focused)

Details: Queued in 2024 in the AESO interconnection queue, co-located at the Genesee Generating Station west of Edmonton. Applied on June 26, 2024, with an expected energization date of January 1, 2027.

Estimated In-Service Date: January 1, 2027

Type: AI

Power Details: Grid and Onsite Gas Gen

Source: AESO Queue

Genesee Data Centre (500 MW)

Announced

Location: Genesee, AB, Canada

Size: 500 MW

Operator: Capital Power

End User: Hyperscalers (AI-focused)

Details: Queued in 2024 in the AESO interconnection queue, co-located at the Genesee Generating Station west of Edmonton. Applied on August 8, 2024, with an expected energization date of February 1, 2027.

Estimated In-Service Date: February 1, 2027

Type: AI

Power Details: Grid and Onsite Gas Gen

Source: AESO Queue

GLDC Load (AESO P2936)

Announced

Location: Fort Saskatchewan, AB, Canada

Size: 1,800 MW

Operator: Undisclosed

End User: Hyperscalers (AI-focused)

Details: Queued on May 14, 2024, in the AESO interconnection queue as a "data load" project. Proposed completion date is under review.

Estimated In-Service Date: Under Review

Type: AI

Power Details: Grid and Onsite Gas Gen

Source: AESO Queue

Keephills Data Centre Phase 1

Announced

Location: Wabamun, AB, Canada

Size: 395 MW

Operator: Undisclosed

End User: Hyperscalers (AI-focused)

Details: Queued on January 28, 2025, in the AESO interconnection queue. Expected energization date of July 1, 2027.

Estimated In-Service Date: July 1, 2027

Type: AI

Power Details: Grid

Source: AESO Queue

Keephills Energy Centre Phase 2

Announced

Location: Wabamun, AB, Canada

Size: 466 MW

Operator: Undisclosed

End User: Hyperscalers (AI-focused)

Details: Queued on January 28, 2025, in the AESO interconnection queue. Expected energization date of July 1, 2028.

Estimated In-Service Date: July 1, 2028

Type: AI

Power Details: Grid and Onsite Gas Gen

Source: AESO Queue

Leedale Load

Announced

Location: Caroline, AB, Canada

Size: 1864 MW

Operator: Undisclosed

End User: Undisclosed

Details: Queued on November 11, 2024, in the AESO interconnection queue. Expected energization date of August 1, 2028.

Estimated In-Service Date: August 1, 2028

Type: AI

Power Details: Grid

Source: AESO Queue

North Calgary One Data Centre MPC Load

Announced

Location: Balzac/Rocky View, AB, Canada

Size: 450 MW

Operator: Undisclosed

End User: Unknown

Details: Queued on September 11, 2024, in the AESO interconnection queue. Expected energization date of March 26, 2027.

Estimated In-Service Date: March 26, 2027

Type: Unknown

Power Details: Grid

Source: AESO Queue

North Calgary Two Data Centre MPC Load

Announced

Location: Balzac/Rocky View, AB, Canada

Size: 450 MW

Operator: Undisclosed

End User: Unknown

Details: Queued on September 11, 2024, in the AESO interconnection queue. Expected energization date of March 26, 2027.

Estimated In-Service Date: March 26, 2027

Type: Unknown

Power Details: Grid

Source: AESO Queue